REVIEW Week (?? totally lost time): Alldays progress at the sight
Team Meeting in the office, meanwhile in front of the office the construction goes on…

REVIEW Week (?? totally lost time): Alldays progress at the sight
Team Meeting in the office, meanwhile in front of the office the construction goes on…

The inner circle
First trials for the doors. And now there needs to be a whole for the water tank. One of the sights benefits: the beach is not far away…

The inner circle
First trials for the doors. And now there needs to be a whole for the water tank. One of the sights benefits: the beach is not far away…

Playfull light
Every evening the sun shows a nice lightshow in the finished classroom. A white line marks the inner concret circle.

Playfull light
Every evening the sun shows a nice lightshow in the finished classroom. A white line marks the inner concret circle.

First finished interlock-wall
Even if the first interlock wall is finished and all roofs are done, there is still a lot of work to do. A reason for a team-meeting in the morfning.

First finished interlock-wall
Even if the first interlock wall is finished and all roofs are done, there is still a lot of work to do. A reason for a team-meeting in the morfning.

It’s time for bricks
The last week the site took a big step: second and third roof of the classrooms are finished and the workers start with the first walls.

It’s time for bricks
The last week the site took a big step: second and third roof of the classrooms are finished and the workers start with the first walls.

One day before holidays and some finished sections
First finished roof: Time to take a picture of all workers at the site The concrete chain for the works on the second ringbeam at the future office. Meanwhile the flooring is done on one of the classrooms.

One day before holidays and some finished sections
First finished roof: Time to take a picture of all workers at the site The concrete chain for the works on the second ringbeam at the future office. Meanwhile the flooring is done on one of the classrooms.

Down to the floor
The workers go fast forward. The building gets it’s floor.