It’s time for bricks

The last week the site took a big step: second and third roof of the classrooms are finished and the workers start with the first walls.

It’s time for bricks

The last week the site took a big step: second and third roof of the classrooms are finished and the workers start with the first walls.

One day before holidays and some finished sections

First finished roof: Time to take a picture of all workers at the site The concrete chain for the works on the second ringbeam at the future office. Meanwhile the flooring is done on one of the classrooms.

One day before holidays and some finished sections

First finished roof: Time to take a picture of all workers at the site The concrete chain for the works on the second ringbeam at the future office. Meanwhile the flooring is done on one of the classrooms.

Down to the floor

The workers go fast forward. The building gets it’s floor.

Down to the floor

The workers go fast forward. The building gets it’s floor.

First roof structure and first Felix at the site

Today the project did a further step: The first roof structure is installed and finally Felix arrived on site.

First roof structure and first Felix at the site

Today the project did a further step: The first roof structure is installed and finally Felix arrived on site.

1st of April

A lot of concrete has been poured today: Works on the second ringbeam have been almost completed, as well as the plinth beam at the caretakers house. Further more we did a new set of tiles, featuring leaf inlays.

1st of April

A lot of concrete has been poured today: Works on the second ringbeam have been almost completed, as well as the plinth beam at the caretakers house. Further more we did a new set of tiles, featuring leaf inlays.

Fully Comet – high life on the site

F like Francis – the Trucks in Sri Lanka are really colourfull and for us they bring the cement. In the morning at 10:00 with 30 degrees everyone is working hard. The welder are the happy ones who can work

Fully Comet – high life on the site

F like Francis – the Trucks in Sri Lanka are really colourfull and for us they bring the cement. In the morning at 10:00 with 30 degrees everyone is working hard. The welder are the happy ones who can work

We go for tiles and more

In Sri Lanka the workers got to the site even on saturday. We are happy about it, because of the rain on friday moring we have a little delay to compensate. Our new support in the office. Carolin arrived on

We go for tiles and more

In Sri Lanka the workers got to the site even on saturday. We are happy about it, because of the rain on friday moring we have a little delay to compensate. Our new support in the office. Carolin arrived on

Waiting for more material

The morning starts with rain and we are still waiting for the delivery of more bricks and wooden 2by2s. When it rains in the morning the laborers go home again and don’t work at that day even if it stops

Waiting for more material

The morning starts with rain and we are still waiting for the delivery of more bricks and wooden 2by2s. When it rains in the morning the laborers go home again and don’t work at that day even if it stops

Working on the first part of the Ringbeams

The material is deliverd by the colorfull sri lankan lorrys. The furniture is ready for use.There is still the palmtree leaf-roof missing at the little office building to make some shade. To get special prepared bananaleafs it will take two

Working on the first part of the Ringbeams

The material is deliverd by the colorfull sri lankan lorrys. The furniture is ready for use.There is still the palmtree leaf-roof missing at the little office building to make some shade. To get special prepared bananaleafs it will take two